Data centres turn to private gas power plants for artificial intelligence

In the face of long lead times, data centre developers choose to build their own gas plants in the United States.

3 min read

Automatic translation of the original article from French. Lire en français

Photo illustrating: data center natural gas turbines
Photo: Lamiot · CC BY-SA 4.0. Source: Wikimedia Commons

Key points

  • According to MIT Technology Review, connecting a data center to the power grid can take up to a decade.
  • According to Cleanview, more than 100 private gas plant projects have been announced in the United States with a capacity of more than 115 gigawatts.
  • According to BloombergNEF, speed research is the main motivation for developers to opt for on-site power supply.
  • According to MIT Technology Review, the xAI campus in Memphis already used gas turbines as early as 2024.

Barriers to the electrical connection of infrastructure

The rapid development of artificial intelligence faces a major logistical and technical challenge in energy supply. According to information reported by MIT Technology Review, one of the main obstacles to the opening of a new data centre is obtaining the necessary authorisations to connect to the public electricity network. This administrative and technical procedure can be particularly lengthy, with waiting times up to a decade. In the face of this perceived excessive time constraint, some actors in the sector refuse to wait and choose to erect their own off-grid power generation facilities, also referred to as behind-grid or natural gas installations.

Previous xAI campus in Memphis

This strategy of freeing itself from the public network is not entirely new, although it has been democratised recently. The xAI campus located in Memphis was thus illustrated by the use of dozens of natural gas turbines as early as 2024, some of which were operated in the absence of the required permits. At that time, this initiative was a notable exception and quickly attracted the attention of local regulators. MIT Technology Review states that this infrastructure is still subject to ongoing legal proceedings. However, while this approach was a singularity in the past, it subsequently became a much more widespread option in the technology industry.

Multiplication of projects identified in the United States

The data published by the market intelligence company Cleanview illustrate the extent of this change. In October 2026, data centre developers formalized projects for the construction of more than one hundred private gas plants at sites in the United States. The cumulative capacity of these planned structures is more than 115 gigawatts, representing more than double the peak peak electricity demand for the state of California. The organization also states that the vast majority of these announcements have been registered since the beginning of 2025. However, these prospects need to be nuanced, since only a very small part of these plants are currently in the construction phase or are already operational, and the implementation of all these projects remains uncertain.

The search for speed as the main engine

The choice of a clean power plant typically results in higher financial costs than simply connecting to the conventional power grid. However, the frenzy surrounding the development of artificial intelligence pushes developers to agree to significant additional costs to accelerate the commissioning of their equipment. According to Musfika Mishi, an analyst at BloombergNEF's energy consulting firm, the search for speed is currently the main incentive for data centres to opt for autonomous power supply on site, ahead of purely economic considerations.

The heavy process of network operators

In order to fully understand the origin of this trend, we must examine the burdensome nature of the usual approaches. Where a promoter wishes to establish a new energy-efficient industrial facility, such as a data centre, it is imperative that a request for a connection be made to a local electricity supplier or regional system operator. This approach initiates a complex journey spanning several years. During this period, network planners conduct in-depth analyses to determine the necessary adaptations to safely deliver electricity, without compromising the overall reliability of the system. Major modernizations may be necessary, including the creation of new power transmission lines or the installation of higher capacity transformers, investments that may be funded in part by the project proponent. Rather than be subject to this binding schedule, data centre designers choose to focus on autonomous energy solutions.

To go further

Calculate with a free tool

To understand the terms

PER (price / profit ratio)
Course of a share divided by profit per share over 12 months. A RIP of 20 means that the share pays 20 times its annual profit.
Stock market capitalization
Number of shares multiplied by the price: the total value of the company on the stock exchange.
Analyst consensus
Average of opinions published by financial analysts. These are third-party opinions, not certainties.

Sources

Sources consulted for this article. The links open the publisher's website.

  1. 1.
    MIT Technology Review
    Data centers are getting their own natural gas power plants(opens in new tab)

    technologyreview.com

Also read